Skip to content
← Research Notes
Jurisdiction DataTexas · Michigan · Indiana · Data Centers

The cost of a data center is not in the land or the shell anymore

Abilene closed $11.6 billion in one financing round. Saline Township priced permission in a consent judgment. Lebanon, Indiana prepaid its entitlement at district scale. Where data-center cost actually lives now, with the numbers.

On May 22, 2025, Crusoe, Blue Owl Capital, and Primary Digital Infrastructure closed an $11.6 billion financing package to fund six data-center buildings outside Abilene, Texas. One round, six buildings. The full campus runs to eight buildings and 1.2 gigawatts inside a $15 billion joint venture, with each building designed to hold up to 50,000 NVIDIA GB200 NVL72 racks and the campus targeting roughly 400,000 GPUs. Somewhere inside those numbers is the price of the dirt, and you would need a footnote to find it.

The land stopped being the cost.

For most of the history of industrial real estate, the pro forma was mostly site and shell, and the site was the variable a development team could actually win on. The Abilene record shows how completely that logic has inverted at hyperscale. Construction started in June 2024 on a parcel inside a Lancium Clean Campus, ground purpose-built to accept industrial load next to West Texas wind generation, and Phase 1 went live on Oracle Cloud Infrastructure on September 30, 2025, fifteen months later. The things that made the deal financeable were never the acreage. They were the closed-loop, zero-evaporation liquid cooling that removed the water fight before it started, the wind surplus that removed the transmission fight, and a county posture, anchored by the Abilene Industrial Foundation's long public record of supporting large-capex siting, that removed the hearing fight. Our read on the site was 82 out of 100 before the first pad was poured, and none of the points came from land price.

What does permission cost when the county says no?

Saline Township, Michigan put a literal invoice on it. Related Digital's 575-acre rezoning for a $7 billion campus was denied 4-1 on September 10, 2025. RD Michigan Property Owner I LLC and landowners sued two days later, the board voted 4-1 to pursue settlement on October 1, and the October 15 consent judgment reads like a rate card: a $4 million farmland trust, a $2 million community fund, $7 million for the Saline Area Fire Department, and $500,000 each for the Clinton Township and Manchester fire departments. Fourteen million dollars, to convert a denial into an authorization.

Cash is the visible half. The Saline judgment also carries terms that never hit a wire transfer but behave exactly like cost: a 55-decibel noise limit, Michigan Avenue access only, a ban on high-water-use evaporative cooling, no material expansion, and decommissioning security. Every one of those is a constraint an engineering team now has to buy its way around for the life of the asset. The cooling ban alone dictates the thermal design of a campus that would go on to contract for 1,383 MW of power.

Then there is the power contract, which the pro forma files under revenue enablement and should file under cost. The Michigan Public Service Commission approved DTE's special contracts 3-0 on December 18, 2025, and the conditions are the point: a 19-year minimum duration, an 80% minimum billing demand, customer-funded energy storage, quarterly reporting, and a requirement that DTE file a generally applicable large-load tariff within 90 days. An 80% minimum billing demand means the campus pays for four-fifths of its contracted load whether or not it draws a watt. That is a floor under operating cost, signed for 19 years. And the regulatory meter kept running: Attorney General Dana Nessel intervened in November 2025 and moved to reopen the approval on February 5, 2026 over revised "aggregate revenues" language. A term-sheet fight at a utility commission is a cost line too. It is paid in counsel and in risk premium.

Can you prepay the entitlement instead?

Lebanon, Indiana says yes, provided a state does it for you first. The LEAP record shows Indiana's economic development corporation quietly assembling roughly 9,000 acres in Boone County starting in November 2021 and putting nearly $1 billion into land and infrastructure. Lebanon's council adopted the LEAP planned unit development unanimously in August 2023, and data centers became a Permitted Use in the Industrial Mega Site subdistrict. So when Meta's 1,500-acre, 13-building, $10 billion campus reached the Plan Commission in August 2025, approval was administrative. No public hearing. No discretionary vote. Ground broke in February 2026.

The entitlement cost did not disappear in Lebanon. It was paid earlier, by someone else, at district scale, and Meta compensated the jurisdiction on the way in: the council approved an $800 million initial-phase incentive package in November 2024, with up to $4.8 billion available across six phases. What Meta carries instead of hearing risk is infrastructure timing. The Wabash Valley Power Alliance's 1,200 MW MISO filing is approved, but the physical 345 kV and 138 kV transmission lines target December 2026 completion, and a by-right campus that cannot energize is a very expensive shed.

None of Saline's costs arrived by surprise, which is the part worth dwelling on. Our pre-filing read on the site in early 2025 was 35 out of 100: A-1 agricultural zoning with no industrial precedent, a five-member board with two or three members likely opposed, a DTE special-contract approval running separately at the MPSC, and wetlands, wells, noise, and fire response flagged as stress points. The read recommended budgeting for litigation and concessions before anyone filed. The post-settlement read rose to 59, still held under 70 by the AG's reopening motion and the live permitting tail. Every dollar the sponsor eventually paid was visible in the record as a category, months before it acquired a number.

Line the three ledgers up and the pattern is hard to miss. Abilene spent its money on design choices that deleted objections before they were raised. Saline spent $14 million plus a lawsuit plus a court-supervised operating envelope to purchase permission after the objections won a vote. Lebanon inherited a prepaid entitlement and pays in incentive commitments and transmission schedule risk.

Same asset class. Three different places the cost went to live.

Why do screening models keep missing this?

Because most of them are still land-led. A site memo that opens with price per acre and zoning classification is answering the 2015 question. The 2026 question is what the permission and the power terms cost to carry, and those numbers dwarf the dirt. Saline's community package alone exceeds what large tracts of rural Michigan farmland trade for in total, and the 19-year contract floor beneath it is larger still. Even Abilene, the clean case, showed a cost the entitlement never touches: in early 2026, Oracle and OpenAI dropped plans to expand beyond the funded eight-building footprint, with Microsoft reported picking up two adjacent buildings and an on-site power plant and Meta in discussions, with NVIDIA participating, to absorb capacity. Fully financed, fully entitled, and the demand stack still got reshuffled mid-build. Any data-center screen that prices land risk in detail and everything else in a footnote has the proportions backwards.

My bet, stated plainly: within two years the standard data-center site memo leads with the power-contract term sheet and a concession estimate, and land basis moves to the appendix. If deal teams in 2028 are still opening committee meetings with price per acre, I called this wrong and the old pro forma deserves an apology. In the meantime, run one honest test on your own pipeline: put an 80% billing floor under your contracted load, add a Saline-shaped community package, and watch which line moves your returns. It will not be the land.

This analysis is a source-cited research summary drawn from public records, not legal advice. It can contain errors and should be verified independently before any investment decision.

Before the diligence clock starts

This is the same read RealClear runs against a live site: zoning, approval pathway, infrastructure, and community posture — every finding pinned to a named source.

Source-cited research summary. Not legal advice. Verify independently before making investment decisions.