Case File · Abilene, Taylor County, Texas
Crusoe, Blue Owl Capital, and Primary Digital Infrastructure financed and began building the flagship Stargate campus in Abilene, Texas. 1.2 GW across eight buildings. Phase 1 went live on Oracle Cloud Infrastructure on September 30, 2025. Closed-loop, zero-evaporation liquid cooling eliminated the water politics that killed data centers in San Marcos, Tucson, and Chesapeake.
Cited site read: 82/100 before the first pad was poured.
$15B
JV Size
$11.6B
2025 Financing
1.2 GW
Campus Power
8
Buildings
Sep 2025
Phase 1 Live
82/100
RealClear Score
Abilene, Texas · 2024 — 2026
From a Lancium Clean Campus lot to an $11.6 billion live AI factory in 18 months. Every financing close. Every silicon delivery. Every phase milestone.
June 2024
Stargate Abilene construction begins
Crusoe Energy begins construction on the initial phase of the Abilene, Texas campus — the flagship site for OpenAI's Stargate initiative. Phase 1 is designed for over 200 MW of capacity. The campus sits on land developed using the Lancium Clean Campus model, built around closed-loop, direct-to-chip liquid cooling with zero-water evaporation.
March 2025
Phase 2 construction begins — six additional buildings
Crusoe, Blue Owl Capital, and Primary Digital Infrastructure break ground on six additional data center buildings at Abilene, targeting mid-2026 energization. Each building is designed to support up to 50,000 NVIDIA GB200 NVL72 units on a unified network fabric. Total campus capacity: 1.2 GW across eight buildings.
May 22, 2025
$11.6 billion financing package closes
Crusoe Energy, Blue Owl Capital, and Primary Digital Infrastructure announce the second phase of their $15 billion joint venture to develop the 1.2 GW Abilene campus. The $11.6 billion funding package supports construction of the six additional data center buildings. The financing is one of the largest single data-center debt raises on record.
June 2025
First NVIDIA GB200 racks delivered
First NVIDIA GB200 racks are delivered to Phase 1. Early training and inference workloads begin running at the facility while commissioning continues. The campus is designed to ultimately support approximately 400,000 GPU units.
September 30, 2025
Phase 1 goes live on Oracle Cloud Infrastructure
Crusoe announces Phase 1 of the Abilene data center is live, hosted on Oracle Cloud Infrastructure. CEO Chase Lochmiller calls the facility 'the new blueprint for large-scale data center development.' Oracle EVP Mahesh Thiagarajan praises Crusoe's design and construction execution. The Stargate project — led by OpenAI, SoftBank, and Oracle — is framed as a multi-phase, $500 billion national AI infrastructure build-out.
Early 2026
Oracle and OpenAI drop flagship expansion plans
Oracle and OpenAI cancel plans to further expand the flagship Abilene Stargate site. Microsoft is reported to be picking up two adjacent AI-factory buildings and an on-site power plant from Crusoe. Meta is in discussions with Crusoe — with NVIDIA's participation — to absorb additional capacity. The eight-building footprint is fully financed but the demand stack is being reshuffled among hyperscalers.
The Parties at the Table
A Denver AI infrastructure firm. A private credit giant. Oracle's cloud leadership. And a hyperscaler demand shuffle mid-build.
Chase Lochmiller
Co-founder & CEO, Crusoe
Documented Record
Publicly announced Phase 1 go-live on Oracle Cloud Infrastructure, describing the facility as 'the new blueprint for large-scale data center development.'
Drove the site selection, Lancium partnership, and joint-venture structure. His public framing positions Crusoe as the primary operator of the flagship Stargate facility — not Oracle or OpenAI directly.
Mahesh Thiagarajan
EVP, Oracle Cloud Infrastructure
Documented Record
Oracle press statement praised Crusoe's leadership in AI data-center design, engineering, and construction at the September 30, 2025 go-live milestone.
Oracle's operational champion for the Stargate partnership. OCI hosts the Phase 1 workloads — meaning Oracle's revenue is tied to Crusoe's execution. This creates unusually strong alignment.
Sam Altman
CEO, OpenAI
Documented Record
Announced the $500 billion Stargate initiative alongside Oracle and SoftBank in early 2025; reports in 2026 indicate OpenAI dropped plans to expand beyond the current eight-building footprint in Abilene.
Originally the demand driver for flagship expansion. The early-2026 decision to pause Abilene expansion — while Meta and Microsoft absorb capacity — suggests OpenAI's compute forecast has changed, not that the site has soured.
Blue Owl Capital
Private Credit Partner
Documented Record
Co-anchored the $11.6 billion May 2025 financing and the underlying $15 billion JV with Crusoe and Primary Digital.
Blue Owl's participation signals that institutional private credit has accepted hyperscale AI as an investable asset class. Their involvement is the primary de-risking signal at the capital-stack level.
Primary Digital Infrastructure
JV Partner / Asset Manager
Documented Record
Co-led the $15B joint venture and is responsible for long-term asset management of the Abilene campus.
Provides the institutional real-estate operating discipline that a pure compute company like Crusoe does not have in-house. Their participation signals the asset is being built to institutional hold standards.
NVIDIA
Silicon Supplier / Meta Participant
Documented Record
Delivered the first GB200 NVL72 racks in June 2025; 2026 reports describe NVIDIA participation in the Meta discussions to absorb Abilene capacity.
NVIDIA's dual role — silicon supplier and participant in the capacity reshuffle — makes them the single most informed party about demand economics at Abilene. Their involvement is a strong positive signal for absorption.
Design Choices That Eliminated Opposition
The Abilene design deliberately preempted every objection that has killed data centers in Arizona, Virginia, and Central Texas.
Closed-Loop Liquid Cooling
Lancium Clean Campus design · Zero-water evaporation
The Crusoe facilities use closed-loop, direct-to-chip liquid cooling with zero-water evaporation. This single design decision neutralizes the opposition argument that killed San Marcos (70,000 gal/day during drought), Project Blue Tucson (desert water), and Chesapeake (community water politics). In Abilene, there is simply no water story to fight.
“Crusoe has proven its leadership in AI data center design, engineering and construction.”
Regional Wind Power Match
West Texas wind surplus · ERCOT interconnect
West Texas generates more wind power than the region consumes. Co-locating 1.2 GW of compute load with surplus generation eliminates the transmission constraint that is pausing Microsoft in Licking County, Ohio. The Abilene siting decision was a power-infrastructure decision before it was a real-estate decision.
Abilene Industrial Foundation
Local development authority · Pro-growth posture
The Abilene Industrial Foundation has a long-documented record supporting large-capex industrial siting. The political posture at the county and municipal level is the inverse of what Project Blue faced in Tucson or what Gigaland faced in Fauquier County. The same proposal in those jurisdictions would not have reached financial close.
The Pre-Filing Research
The opposite of San Marcos. Low-water design, power-matched siting, and a receptive local political posture.
Site Analysis
Crusoe / OpenAI Stargate Flagship
Abilene, Taylor County, TX — 8 buildings, 1.2 GW, $15B JV
Favorable Source Records
Approval Pathway
Taylor County by-right industrial → ERCOT Study CLEAR
Water Risk
Power Signal
Execution Risk
Recommendation
STRONG GO. Low-water cooling design, regional wind surplus, and a receptive Abilene Industrial Foundation eliminate the three risk categories that killed Project Blue, Chesapeake, and San Marcos. Secondary risk is macro-level demand: Oracle / OpenAI cancelled flagship expansion plans in early 2026, and Meta is in talks to absorb capacity with NVIDIA participation.
The Pre-Flight Checklist
Every enabler that made Abilene a financing-ready site was visible in public records before financial close.
Lancium Clean Campus land — purpose-built for hyperscale
Zoning reviewThe Abilene parcel is part of a Lancium Clean Campus: a site purpose-built to accept hyperscale industrial load adjacent to wind generation. The entitlement envelope is pre-cleared at the county level. A pre-filing source review surfaces this as a by-right, not a rezoning, situation — the single biggest accelerator for any large-capex DC.
Zero-evaporation cooling = zero water politics
Community risk reviewThe facility's closed-loop liquid cooling eliminates the water-scarcity narrative that has killed every denied data center in 2025. A RealClear analysis scores 'community water risk' as LOW only when water consumption is structurally negligible. Abilene passes that test. San Marcos, Chesapeake, and Project Blue Tucson did not.
ERCOT wind surplus + co-located generation
Power AnalysisWest Texas generates wind power faster than the local grid can consume it. Co-locating 1.2 GW of AI compute with generation surplus eliminates transmission-cost exposure and avoids the interconnection queue delay that is pausing the Microsoft Licking County project in Ohio.
Abilene Industrial Foundation on record supporting DC siting
Political AnalysisThe Foundation has publicly supported industrial growth, including data centers, for years. Political risk at the county and city level is near-zero compared to what Amazon's Project Blue faced in Tucson. The Community risk review would flag the Foundation as an institutional ally, not a veto risk.
Private credit acceptance — $11.6B closed in a single round
Capital SignalBlue Owl Capital's $11.6 billion close is the single strongest signal that the Abilene campus is considered investment-grade by institutional private credit. The financing itself is a risk-marker: institutional capital has already validated the underlying site, operator, and demand profile.
Secondary hyperscaler absorption — Meta, Microsoft, NVIDIA
Demand SignalWhen Oracle and OpenAI dropped flagship expansion plans in early 2026, Microsoft and Meta (with NVIDIA's participation) stepped in to absorb capacity. The campus is demand-redundant at the hyperscaler level — an unusual structural hedge against single-tenant obsolescence risk.
What Happened Next
The entitlement path was clear. The demand stack has been reshuffled. The asset is already operational.
Phase 1
Live on OCI — September 30, 2025
Phase 1 came online on schedule and is now running training and inference workloads for Oracle Cloud Infrastructure customers. Construction began in June 2024; first silicon delivered June 2025.
Phase 2
Six More Buildings — Mid-2026 Target
The six additional buildings funded by the $11.6B Blue Owl / Primary Digital financing are targeted for mid-2026 energization. Full campus: 1.2 GW across 8 buildings, approximately 400,000 GPUs.
Demand Reshuffle
Oracle / OpenAI Drop Expansion Plans
In early 2026, Oracle and OpenAI dropped plans to expand beyond the funded eight-building footprint. Microsoft picked up two adjacent AI factory buildings and an on-site power plant. Meta — with NVIDIA — is in discussions for additional capacity.
Stargate Program Context
$500B OpenAI / SoftBank / Oracle Initiative
Abilene is positioned as the flagship location for the broader, multi-phase $500 billion Stargate AI infrastructure initiative led by OpenAI, SoftBank, and Oracle. Additional Stargate sites are under evaluation — but the Abilene asset is already in revenue.
This Is Entitlement Research
Abilene is the template: site selection drives entitlement outcome. The difference between a 82 and a 12 is not execution — it's design intent before financial close.