Power is the second vote: the approval your zoning win doesn't cover
Saline Township's land fight ended with a consent judgment on October 15, 2025. The project's power approval was still being contested in February 2026. Data centers need two permissions, and they run on different calendars.
The land-use fight over the Stargate data center campus in Saline Township, Michigan ended on October 15, 2025, when a consent judgment resolved the developer's lawsuit and authorized the project subject to detailed restrictions. If you stopped reading the record there, you would call the entitlement done.
The power fight was still going four months later.
In November 2025, Michigan's Attorney General intervened in the utility's special-contract case. The Michigan Public Service Commission did not approve the contracts until December 18, 2025, and it attached real conditions when it did. On February 5, 2026, the Attorney General moved to reopen the approval. Nothing about the township's zoning, the consent judgment, or the $14 million in community commitments could touch any of that, because it was happening in a different forum, under different law, in front of different opponents.
This is the structural fact I think most data-center pro formas still get wrong. A hyperscale campus does not need one permission. It needs two: permission to use the land and permission to draw the load. They are decided by different bodies, on different calendars, and winning the first buys you nothing in the second. The Saline Township record is the cleanest demonstration in our case files, so let us walk it.
Track one: the land, settled in five weeks
The local fight was fast and brutal. The developer asked to rezone roughly 575 acres of A-1 agricultural land to industrial for a multi-building campus, with development described on fewer than 250 acres. On September 10, 2025, the township board denied it 4-1. Two days later, RD Michigan Property Owner I LLC and landowners sued in Washtenaw County Circuit Court on three counts (exclusionary zoning, declaratory relief and violation of law, due process). On October 1, the board voted 4-1 to pursue settlement. On October 15, the consent judgment entered.
Denial to resolution: five weeks. And the settlement terms are a price list of what local permission actually cost: a $4 million farmland trust, a $2 million community fund, $7 million for the Saline Area Fire Department, $500,000 each for two neighboring townships' fire departments, a 55-decibel noise limit, Michigan Avenue access only, no high-water-use evaporative cooling, no material expansion, and decommissioning security.
Note the careful language, because the record demands it. This was a litigation-and-settlement path, not a clean rezoning approval, and a consent judgment is a legal settlement rather than proof of what any court would have ruled. But as a practical matter, by mid-October the land question had an answer. On October 30, the Governor, OpenAI, Oracle, and Related Digital announced the site publicly, with the state calling it the largest one-time investment in Michigan history and citing 2,500 union construction jobs and more than 450 jobs on site.
Track one: closed.
Track two: the load, contested into the next year
Now watch the second track run right past the celebration.
The campus needs contracted power at a scale that required Michigan Public Service Commission approval of special contracts totaling 1,383 MW. In November 2025, Attorney General Dana Nessel intervened in that case and asked for a formal public hearing on whether other ratepayers could be exposed to project-related costs. Critics attacked the expedited review through December. On December 18, 2025, the MPSC approved the contracts 3-0, with conditions that reshape the deal's economics: a 19-year minimum duration, an 80% minimum billing demand, customer-funded energy storage, quarterly reporting, and a requirement that the utility file a generally applicable large-load tariff within 90 days.
Then it kept going. On February 5, 2026, the Attorney General moved to reopen the approval over revised contract language and related battery-storage agreements. A separate resident challenge to the settlement was turned away on February 20 as too late. By March 2026 the site was in active construction, pylons finished and gravel hauling roughly 60% complete, while the power approval that feeds it still had a live regulatory challenge attached.
Different forum, different clock. The township could not have saved the project at the MPSC, and the MPSC could not have saved it at the township. Each track held its own veto.
Even the gold-standard site has a power clock
Here is what makes this a structural rule rather than a Michigan quirk. Take the site our case files score highest on entitlement: Meta's campus in Lebanon, Indiana, inside the purpose-built LEAP district. Land permission there was locked in August 2023, when the city council adopted a PUD making data centers a by-right use. No discretionary hearings, no rezoning fight, a $10 billion groundbreaking in February 2026.
And the binding constraint at LEAP? Power. The Wabash Valley Power Alliance's 1,200 MW generation filing cleared MISO, but the physical 345 kV and 138 kV transmission targets December 2026 completion. On the best entitlement site in our files, the schedule risk that remains is entirely on the second track. That risk is execution rather than approval, which is a better class of problem, but it is the same lesson: the land calendar and the load calendar are independent, and the slower one sets your in-service date.
Why the power track is politically different
The land track's opponents are neighbors. The power track's opponents are institutions.
At a township podium you face residents worried about farmland, noise, traffic, and water, and the toolkit for that fight is community engagement, design concessions, and money. In a utility docket you face attorneys general and ratepayer advocates, and the argument is about cost allocation: who pays for the grid this load requires. Community benefits packages do not answer that question. The Saline record shows the two opponent classes explicitly; the AG's intervention was about ratepayer protections and utility process, not about the township's zoning at all.
That also means the power track imports statewide politics into your project whether you invite them or not. Michigan's new large-load tariff requirement exists because this one project forced the question. Every subsequent large-load customer in the state will negotiate inside rules this fight wrote.
How to underwrite two calendars
The practical takeaways are short. Model the load approval as its own critical path with its own probability of delay, not as a line item inside "utilities." Ask, before land assembly, which body approves contracted power at your scale, whether an intervenor class exists there, and what precedent your project would set, because precedent-setting dockets run slow. And read both records, because a jurisdiction read that covers the zoning code but not the utility docket is half a read.
My bet, stated plainly: within the next 18 months, state utility proceedings overtake local zoning as the place where large data-center projects most often stall, because the moratorium wave is teaching developers to pick friendly counties while the ratepayer question stays unresolved almost everywhere. If by the end of 2027 the contested-project ledger still shows zoning as the dominant chokepoint, I called it wrong. Track it with me; the dockets are public.
This analysis is a source-cited research summary drawn from public records, not legal advice. It can contain errors and should be verified independently before any investment decision.
Before the diligence clock starts
This is the same read RealClear runs against a live site: zoning, approval pathway, infrastructure, and community posture — every finding pinned to a named source.
Source-cited research summary. Not legal advice. Verify independently before making investment decisions.