Clarksville / Montgomery County — Tennessee
Clarksville, Montgomery County, Tennessee
CLEAR PATH
Trajectory: No moratorium activity. No restrictive zoning amendments. Tennessee expanded DC incentives (HB 2182 in 2024). Google continues expanding ($2.5B+ cumulative).
Last updated 2026-03-29
Investment Thesis
By-right approval in industrial zones, TVA power infrastructure, zero organized opposition, and Google operating successfully since 2019. Tennessee has expanded DC incentives.
Google has operated in Clarksville since 2019. The data center is permitted by-right in commercial and industrial zones through administrative review — no CUP, no public hearing, no council vote required. TVA provides the power. Tennessee expanded DC tax incentives in 2024 with HB 2182. After 12+ search queries across local news, Reddit, Change.org, and municipal records, we found zero organized opposition. The biggest controversy is whether TVA should keep a coal plant open to serve data center demand.
By-right approval in commercial and industrial zones through P&Z administrative review. This is the least discretionary approval pathway among markets that still have formal zoning.
Google has invested $2.5B+ and generated $10.6B in economic activity in 2024 across the Montgomery County region.
TVA is one of the largest public power providers in America — and 18% of its industrial load now comes from data centers. 6.2 GW of new generation in the pipeline.
Tennessee is not among the states with DC moratorium bills in 2025-2026. HB 2182 (2024) expanded DC tax exemptions.
Zero organized opposition found across comprehensive search. Google's community grants ($600K+ since 2018) and school funding have built genuine local support.
Inside this score
How the 100 points break down.
Each dimension is scored out of its own weight, and the four add up to the score. A higher score is a clearer market-level path; it is not a likelihood of approval for a parcel.
- Regulatory Riskweight 3024 / 30
What it reads, and where it stops
Measures zoning classification, approval pathway type (by-right, CUP, rezoning), moratorium status, and regulatory trajectory. Higher scores indicate clearer regulatory paths.
Reads the written route and the stated direction of a market's rules as of the edition date. It does not read a particular parcel's zoning, and a rule recorded here can change at the next meeting of the body.
- Infrastructure Readinessweight 2520 / 25
What it reads, and where it stops
Measures utility capacity, grid interconnection availability, water supply adequacy, and infrastructure investment commitments. Higher scores indicate better infrastructure readiness.
Reads the utility, grid, water and investment record for the market. It does not confirm capacity at a given site, and delivery timelines for power and water are separate from entitlement risk.
- Opposition Densityweight 2522 / 25
What it reads, and where it stops
Measures organized opposition groups, petition scale, public hearing attendance, political consequences (elections, recalls), and legal challenges. Higher scores indicate less opposition.
Reads organised opposition that shows on the public record: groups, petitions, hearings, elections and legal challenges. A quiet record is not evidence of support, and a loud one is not a count of votes.
- Approval Timelineweight 2016 / 20
What it reads, and where it stops
Measures historical approval durations, number of sequential approval steps, legal challenges affecting timeline, and demonstrated fast-track capabilities. Higher scores indicate faster approvals.
Reads how long recorded approvals have taken and how many sequential steps they needed. Past duration is a record of what happened, not a schedule for the next application.
24 + 20 + 22 + 16 = 82 of 100 · Clear Path
Dimension Breakdown
How this market scores across four dimensions.
Regulatory Risk
30 pts
By-right in commercial and industrial zones through P&Z administrative review. Google operating since 2019. No DC-specific restrictions. Tennessee has no state or local moratorium.
Score: 24/30. By-right in commercial and industrial zones through administrative review. No DC-specific restrictions. No moratorium. No restrictive amendments.
Infrastructure Readiness
25 pts
TVA — one of the largest public power providers. 18% of industrial load from DCs in 2025. Google on 100% renewable via 413 MW solar PPA. TVA pursuing 6.2 GW new generation. CDE Lightband serves 80,000+ metered homes.
Score: 20/25. TVA provides robust public power. Google on 100% renewable via 413 MW solar PPA. CDE Lightband serves 80,000+ metered homes. TVA pursuing 6.2 GW new generation.
Opposition Density
25 pts
No organized opposition found after 12+ search queries. Google has operated since 2019 with exclusively positive coverage — community grants, school funding, charitable giving.
Score: 22/25. No organized opposition found after comprehensive search. Google's community engagement (grants, school funding) has built local support. Sierra Club's March 2026 criticism targeted TVA's gas plant reliance, not the data center itself.
Approval Timeline
20 pts
By-right P&Z administrative review in industrial zones. Google: announced December 2015, groundbreaking February 2018, opened November 2019.
Score: 16/20. Google: announced December 2015, groundbreaking February 2018, opened November 2019. By-right administrative review eliminates the discretionary hearing that creates delay in other markets.
Key Findings
What the evidence supports.
Data centers permitted by right in commercial and industrial zones through P&Z administrative review.
Montgomery County FAQTennessee HB 2182 (2024) expanded DC tax exemptions to cover affiliated transfers.
Server Country TennesseeGoogle has invested $2.5B+ and generated $10.6B in economic activity in 2024.
Google Data Centers: Montgomery CountyTennessee not among states with DC moratorium bills in 2025-2026.
Good Jobs FirstIncentives & Programs
Why developers are choosing here.
20-year PILOT agreement with Google (December 2015)
Exempting the data center from portions of property taxes for 20 years.
SourceHB 2182 — expanded DC sales/use tax exemptions (2024)
Allows previously-qualified DCs to retain exemption when transferred to affiliate through corporate restructuring.
SourceGoogle community grants — $600,000+ since 2018
Grants to local nonprofits and schools; $300,000 in Goodwill Industries.
SourceDates on the record
Dates on the record.
As of the 29 Mar 2026 edition
No date after the 29 Mar 2026 edition is on the record for Clarksville.
Only dates that this market's own timeline gives. No outcome is named.
Known Risks
No market is risk-free. Here's what to watch.
The credibility of a favorable score depends on honest risk disclosure. These risks are documented in public records.
TVA may keep Cumberland Fossil Plant open due to DC demand — environmental scrutiny
Sierra Club press release (March 2026) criticized TVA's gas plant reliance
Data Gaps
Transparent about what we do not yet know.
- Could not extract verbatim zoning code section numbers from Municode for Clarksville
Recommendation
CLEAR PATH — Score 82/100
Favorable market. By-right approval, TVA infrastructure, and no organized opposition.
From the record
What the public record holds for Clarksville.
Each case file below is a verified public record with its sources attached; each note is a dated research note. They sit beside this market's score; they do not change it.
Notes about Tennessee
- BlueOval SK and the art of restructuring a promiseJurisdiction Data · 26 May 2026
Sector page: Data centers
Get a site-specific cited site memo.
Market-level scores are the first filter. Site-level analysis is where the real risk lives. The cited site-memo queue targets a delivery window confirmed at acceptance of the completed property submission. Complex or thin-record sites can take longer.
Bring us a propertyThe site-memo queue targets a delivery window confirmed at acceptance of the completed property submission. Complex or thin-record sites can take longer.